Intensive work is now underway to push
forward the "Quick Start Package" (for which
implementation can begin within the next twelve months) of
infrastructure projects presented to donors at the March
30-31, 2000 Regional Funding Conference for South East
Europe. Lead Agencies have been selected for the 35
infrastructure projects.
The projects have also been split
into three progressive categories: (A) projects which are
already fully funded and ready to move forward immediately
to the contract stage (this currently covers 9 out of the
35 projects); (B) projects for which lead agencies are now
contacting donors who have expressed interest in
supporting the projects (16 of the 35); and (C) projects
for which funds are fully available but more time is
needed to establish which donors will finance (10 of the
35). The projects in Category "C" will be the
subject of a meeting at the Joint EC/World Bank office
before the end of May.
Dates
on projected start of bidding and work will continue to be
added as the projects develop.
This
table has been replaced.
See
the current status of Infrastructure "Quick
Start" Projects and
Studies,
last updated on October 19, 2001
See
report on Infrastructure for the Regional Funding Conference,
including project descriptions
|