(i) Reconstructing the power system. The
Federation and RS governments place high priority on
reconstructing the power system as one of the primary means to
relaunch economic activity. IDA and other international donors
have been supporting this reconstruction, mainly through the
Emergency Electric Power Reconstruction Project (Cr. No. 2903) and
the Second Electric Power Reconstruction Project (Cr. No. 3071).
Further investments are needed to continue the post-war
reconstruction program.
(ii) Improving cost recovery. Since
the Dayton peace accord, the revenue situation of the three
enterprises, both in terms of tariff levels as well as collection
performance, has improved, particularly for EPBiH. Further
progress is required, however, to reach full cost recovery,
including coverage of normal depreciation charges. This will
require progressive increases in: (i) billing and collection; (ii)
cost efficiency through adequate system repair and maintenance and
commercial trade of electricity within BiH; and (iii) tariff
levels.
(iii) Improving tariff structures. A
recently completed tariff study has shown that average industrial
tariff rates in BiH are not far below economic and financial
costs. By contrast, household rates for all three enterprises are
well below cost levels. The strategy of the Governments and
companies is to gradually raise household rates towards the
economic level in accordance with the financial requirements of
the companies and as the ability of households to pay increases.
(iv) Increasing mutually beneficial power
exchanges between EPBiH, EPM and EPRS. In the period
immediately following the war, power exchanges between the
different parts of BiH were restricted because of the breakdown of
many transmission lines and the existence of three separate
vertically-integrated power enterprises which were reluctant to
cooperate with each other. The exchanges which were made were in
kind and constrained so that net trade between any pair of
companies was always zero or close to it (e.g., exports from one
company to a service area with a power deficit of another company
are offset by imports of the same amount from a power surplus area
of the other company). The development of commercial trade was
also hindered by difficulties in making payments because of a
poorly functioning banking system. More recently, commercial
exchanges have been initated on a limited scale. Re-establishment
of unhindered power exchanges would: (i) permit surplus power of
one company to be used to alleviate shortages of another company
(caused by inadequate generation capacity or by outages of large
generating units or surges in power demand); (ii) reduce
transmission costs by allowing the most direct routes to be used,
regardless of whether these routes cross the territories of the
other companies; and (iii) reduce generating costs by permitting
the lowest cost generating units in the country to be used at each
time of day and year. A Joint Power Coordinating Center (JPCC) was
established in March 1999 to facilitate the eventual economic
dispatching of power for the whole country, but the companies
themselves still maintain responsibility for the physical controls
and are not obliged to accept the recommendations of the JPCC.
Further progress towards improved power exchanges would be
demonstrated by the establishment of more commercial trade
contracts between the three companies, a readiness by the
companies to help each other out in emergencies, and an increasing
acceptance by the three companies of the power dispatch
recommendations of the JPCC.
(v) Power sector reform. Prior to the
war, BiH had a single vertically-integrated socially-owned power
company. There are currently three vertically-integrated companies
(two in the Federation and one in RS) serving three separate
groups of consumers (Bosniacs, Croats and Serbs). The current
arrangements lack the economies of scale and coordination that
existed before the war. They also lack the potential benefits of
competition (lower costs and prices and greater supply quality and
reliability). Until now, although private investors have expressed
some limited interest, there has not been any private sector
investment in the sector. Private involvement, particularly if it
comes from abroad, could bring valuable expertise as well as new
resources for investment. The challenge for the future is to
establish clear policies for reform in the Federation and
Republika Srpska, incorporate these in electricity legislation
which is in tune with developments in the European Union,
establish a regulatory framework, and establish a power sector
structure which is conducive to both the emergence of beneficial
competition and privatization. However, privatization may require
significant third part guarantees in order to reduce perceived
risks.
(vi) Restructuring the coal mine sector in
the Federation. Investments have been carried out to enable
the Federation coal mines to meet the needs of the thermal power
stations of Tuzla and Kakanj over the next several years. In the
medium term the forecast needs of the power stations could be met
from about four low-cost mines. The other mines appear to be
financially and economically unviable. A coal sector restructuring
study is being carried out under Power 2, which will determine
which mines are economically viable, recommend an organizational
structure for these mines, and propose appropriate measures to
protect the incomes of redundant coal miners and help them find
alternative employment.
2. Objectives
The project development objective is to ensure
access to reliable, lower cost electricity, to be supplied with
reduced environmental and safety risks, and improved cost recovery
by suppliers. The component outputs contributing to this objective
include: (i) improved safety at hydropower plants; (ii) reduced
pollution at thermal power plants; (iii) increased transmission
capacity; (iv) increased distribution capacity; (v) improved
operation of the BiH power system on an integrated basis; (vi)
establishment of a legislative and regulatory framework conducive
to competition and eventual privatization; and (vii) institution
building through corporatization of the power companies and
operation on a commercial basis. The project would continue and
substantially complete the post-conflict reconstruction program in
the power sector.
3. Description
The project would focus on restoration of the
400 kV and other high voltage transmission systems, especially
reconstruction of damaged substations. This would help BiH to
restore the pre-war interconnections with the other parts of
former Yugoslavia and eventually to re-join the Union for the
Coordination of Transmission in Europe (UCTE). The project could
also include a Supervisory Control and Data Acquisition (SCADA)
System component to improve power dispatching and facilitate the
operation of the high voltage network within BiH on an integrated
basis. It would include investments in power distribution to
provide electricity to returning refugees and to reconstruct
damaged facilities, thereby relieving serious overloading in some
areas and enable reduction in the high levels of technical
distribution losses. It would cover some investments at hydropower
stations to improve safety and plant availability. Investments at
thermal power stations would be limited to reducing pollution.
Technical assistance would be provided for commercialization of
the power companies and implementation of power sector
restructuring.
Pending completion of the ongoing feasibility
studies on priority investments in power transmission,
distribution and hydropower plants and SCADA, and further
development of proposals by EPBiH and EPRS on environmental
improvements at thermal power stations, it is not possible at this
stage to provide a detailed description of the equipment to be
financed under the project. Similarly, neither the allocation of
the investments covered under the project between the three power
companies, nor cost estimates are currently available. These data
are expected to be available by late November 1999. An order of
magnitude estimate would put total project cost in the US$200
million range.
Transmission Lines
Transmission substations
SCADA/telecommunications
Distribution
Safety investments at hydropower stations
Environmental investments at thermal power stations
Technical assistance for commercialization and establishment of
regulatory framework
The IDA credit would be lent to Bosnia and
Herzegovina and onlent through the Federation Government to EPBiH
and EPM and through the Government of Republika Srpska to EPRS.
Onlending would be at the IDA service charge, for a 20 year term,
including five years of grace.
Co-financing would be provided through parallel
financing arrangements, with each donor responsible for separate
components. As a result, possible delays in implementation of one
donor's component would generally cause little or no delay in
implementation of other donors' components.
The proposed project would be expected to be
completed within a period to be determined by the feasibility
studies, but currently expected to be about three years.
Management of all aspects of project implementation, except those
to be carried out by the Federation and RS Governments (i.e.,
sector reform), would be carried out by EPBiH, EPM and EPRS, who
would be responsible for execution of their respective parts.
Procurement and disbursement of funds would be handled in
accordance with the agreements reached between each donor and
Bosnia and Herzegovina. All three Elektroprivredas have qualified
staff and expert support required for project management. The PIUs
responsible for implementation of Power 2 (The Federal PIU, the
branch PIUs in EPBiH and EPM, and the PIU in EPRS) would be
expected to continue for the proposed project. However, the PIUs
in EPRS and EPM need assistance in procurement-related activities.
A procurement capacity assessment of the implementing agencies
will be carried out by appraisal. The implementation of the
sub-projects would be the responsibility of the local generation,
transmission and distribution entities.
6. Accounts, Auditing and Reporting
The financial management systems of the three
Elektroprivredas will be reviewed by appraisal and appropriate
measures to strengthen these systems would be included under the
project. The financial statements of these companies and the
project accounts would be audited annually by qualified,
independent, external auditors acceptable to IDA and under terms
of reference approved by IDA, as is being done under Power 2. All
audit reports would be made available to IDA within six months
after the end of the fiscal year. The Beneficiaries would prepare
and furnish to IDA quarterly project implementation reports
summarizing the status of procurement and disbursements,
implementation progress for each component, as well as financial
reports in a form acceptable to IDA.
7. Sustainability
Factors critical for sustainability include: (i)
overall macroeconomic progress, which is needed to restore
consumers' ability to pay for electricity; (ii) satisfactory
financial performance of the three Elektroprivredas; and (iii)
satisfactory coordination between the enterprises to operate the
BiH power system in the interest of BiH as a whole. At this time
the prospects for sustainability of Power 3 look to be good.
8. Lessons learned from past operations in the country/sector
The project would build on the successful
performance of Power 1 and Power 2. One lesson learned from these
projects is the importance of ensuring the timely availability of
co-financing. It is proposed to invite donors to participate in
the pre-appraisal and appraisal missions and to hold a power
sector donors' conference following the completion of the draft
final report of the main feasibility study (which will identify
the individual investments and provide cost estimates). This
report is scheduled to be available in late October 1999. A second
lesson is the importance of having strong, well-staffed PIUs. The
PIUs being used for Power 2 would be expected to continue under
Power 3. A third lesson is that progress towards power sector
coordination and reform requires patience and an active role by
the Bank because of the need to gain the agreement of the three
project beneficiaries and the three Governments under the existing
political climate. In practice, only the Bank can perform this
leadership role.
9. Program of Targeted Intervention (PTI) N
10. Environment Aspects (including any public consultation)
Issues:
Transmission lines:
The major issue associated with the restoration
of the transmission system is to assure that the system being
restored is safe with respect to exposure of local residents to
electromagnetic radiation by establishing that the levels are
within acceptable limits (BiH, EU standards, etc.) during
operation.
Transmission substations:
The major issue is the possible presence of
polychlorinated biphenyls (PCBs) in the transformers, or other
equipment in the substations (e.g. condensers), and if found, the
manner in which the PCBs will be disposed of.
Transmission lines:
Other issues are associated with movement of
men, materials, and equipment during construction (noise, dust)
and noise and communication interferences during operation.
Transmission substations:
Minor issues include exposure of local
residents to electromagnetic radiation and noise from restored
substations is within acceptable limits (BiH, EU standards, etc.).
Additionally, if any of the existing transformers have experienced
leaks, there is the possibility of existing soil and/or
groundwater contamination.
Distribution:
A minor issue is associated with disruption to
transport, communications, etc. during the construction phase.
Thermal Power Stations:
Since the objective is to reduce pollution,
there should be no major negative environmental issues. However,
the components as yet have not been defined. In the course of
deciding on specific components, their environmental benefits as
well as possible adverse effects will be identified and evaluated.
11. Contact Point:
Task Manager
Mian Iftikhar Khalil
The World Bank
1818 H Street, NW
Washington D.C. 20433
Telephone: 202-458 4171
Fax: 202-477-7977
Note: This is information on an evolving
project. Certain components may not be necessarily included in the
final project.
See Bosnia page.