Year of commitment and Budget Line

Project Description and Contractor/Partner in brackets:

Contracted/ Allocated: EURO

Contract status (on 01/11/00):

Amount allocated in EURO
(Approximate)

1996 PHARE

EAP: Services for the Office of the Human Rights Ombudsperson for BiH. (Europa)

524,300.00

Completed

524,300.00

1996 PHARE

Support to the Office of the Human Rights Ombudsperson for BiH.

750,000.00

Completed

750,000.00

1996 Obnova

Support to the Commission for Real Property Claims (CRPC) for displaced persons and refugees.

400,000.00

Completed

400,000.00

1996

Total allocated funds in 1996

    

Sub-Total:

1,674,300.00

1997 Obnova

Support to the Commission for Real Property Claims (CRPC) for displaced persons and refugees.

990,000.00

Completed

990,000.00

1997 PHARE

Support to the Human Rights Chamber.

800,000.00

Completed

1,000,000.00

1997

Total allocated funds in 1997

    

Sub-Total:

1,990,000.00

1998 Obnova

Support to the Human Rights Chamber.

330,000.00

Completed

330,000.00

1998 Obnova

Support to the Office of the Human Rights Ombudsperson.

340,000.00

Completed

340,000.00

1998 Obnova

Support to the Commission for Real Property Claims (CRPC) for displaced persons and refugees.

3,361,697.00

Completed

3,400,000.00

1998

Total allocated funds 1998:

        

Sub-Total:

4,070,000.00

1999 Obnova

Support to the Human Rights Chamber.

700,000.00

Completed

700,000.00

    

Support to the Office of the Ombudsperson.

700,000.00

Ongoing

700,000.00

    

Support to the Commission for Real Property Claims (CRPC) for displaced persons and refugees:

1,000,000.00

    

Expansion and start up costs of office.

120,000.00

Completed

    

    

Operational costs.

144,400.00

Completed

    

    

Staff and office costs.

735,600.00

Completed

    

1999 Obnova

Support to the Commission for Real Property Claims (CRPC) for displaced persons and refugees.

2,000,000.00

Ongoing

2,000,000.00

1999

Total allocated funds 1999:

    

Sub-Total:

4,400,000.00

    

Total allocated funds 1996, 1997, 1998 & 1999:

12,134,300.00


The EC reconstruction programme for Bosnia and Herzegovina detailed by sector:
Energy | Water and Waste | Mine Clearance | Transport | Telecommunications | Europe for Sarajevo | Micro Projects | Reconstruction and Return | Social Cohesion and Development | Dayton Institutions | Media and Culture | Economic Regeneration | Institutional Strengthening | Natural Resources | Customs
The World Bank European Commission Top Home Search Site Map Contact